4 answers
Asked
519 views
Software Engineers; How long is your average work day?
I'm just doing some research for a class of mine and i was wondering how long you work each day.
Login to comment
4 answers
Updated
Tony’s Answer
Hi David,
As you're doing a research for a class and I don't want to give you a false information. It depends on a lot of things to know the average work hours in a day for someone working as software engineer. If you have to come with a number, the range can be wide from 8 - 16 hours based on your experience on a task and the deadline to release it. You cannot say that you will only work 8 hours a day and requesting to delay the project.
Good luck on your research!!!
As you're doing a research for a class and I don't want to give you a false information. It depends on a lot of things to know the average work hours in a day for someone working as software engineer. If you have to come with a number, the range can be wide from 8 - 16 hours based on your experience on a task and the deadline to release it. You cannot say that you will only work 8 hours a day and requesting to delay the project.
Good luck on your research!!!
Updated
Joe’s Answer
Typically, my days are usually 8 to 9 hours, but this can vary tremendously, depending on my projects and deliverables. I tend to have a very flexible work schedule, as it is outcome based, not necessarily hours in seat.
Updated
Dhanabal’s Answer
It depends on the team and commitments you are working on.
Usually my work time is 6-8 hrs as a programmer.
When I lead any team or driving some project it may increase to cover other work also , that time it would be 8-9 hrs ..
Some companies support more work life balance , there you could see always < 8 hrs work should be committed / loaded
Thanks
Usually my work time is 6-8 hrs as a programmer.
When I lead any team or driving some project it may increase to cover other work also , that time it would be 8-9 hrs ..
Some companies support more work life balance , there you could see always < 8 hrs work should be committed / loaded
Thanks
Updated
Chris’s Answer
In my experience, work days for a programmer fall into two categories - normal days and crunch time. On normal days, I worked 8 to 9 hours. However, as we approach deadlines the team ends up putting in extra time to make the deadline - usually 10 to 12 hours, sometimes longer. This usually doesn't last for more than 2 to 3 weeks.
I agree with Tony - once your team sets the schedule for the project , it is a commitment. If necessary, the team is expected to work longer days to meet the project dates.
I agree with Tony - once your team sets the schedule for the project , it is a commitment. If necessary, the team is expected to work longer days to meet the project dates.